Reinforcement steel wastage calculator

Compare the weight of steel in your bar bending schedule with what the store issued for the same work.

The work needed–
–
– over what the work needed

Starts with a sample entry. Nothing you type leaves this page.

How the sum works

The steel needed is the weight from the bar bending schedule for the work completed.

The excess is the steel issued minus that weight. Offcuts and laps beyond the schedule fall inside your wastage allowance; anything above it needs an explanation.

Leave the second field at 1000 unless your schedule is in a different unit.

This is one site, one day

ERP Infra does the same sum for every site and every material, every day, from what the site already enters.

Book a free demo

Questions people ask

How is steel wastage calculated on site?
Subtract the bar bending schedule weight for the completed work from the steel issued, and divide by the schedule weight. 44,600 kg issued against 42,000 kg scheduled is 2,600 kg over, or 6.2%.
Where does steel go missing?
In offcuts that are not reused, bars cut to the wrong length, steel moved to another site without a record, and scrap sold without being weighed.

Let’s put every site on one screen.

Tell us how many projects and sites you run. We will walk you through the system on a call and suggest where a pilot would pay back first.

Book a free demo on WhatsApp
Phone and WhatsApp: +91 92569 97690 Email: flip.retail1@gmail.com B-2, B203 Brij Villa, Rajendra Marg, Bapu Nagar, Jaipur 302015, India