What is committed cost on a construction project?

Committed cost is money you have already promised to spend but have not yet been billed for: purchase orders placed, work orders issued, machines on hire. Budget minus actual cost minus committed cost is the true balance left on a project.

A project can look healthy on paid bills while the orders already placed have taken it over budget. Committed cost is the figure that shows this before the bills arrive.

Formula

Balance = budget − actual cost − committed cost

Worked example

Budget 8.40 million. Actual cost to date 4.91 million. Orders placed but not yet received 0.62 million. The real balance is 2.87 million, not 3.49 million.

In ERP Infra

Budget, committed, actual and balance are shown side by side for every project and every site.

Cost overruns: how it works

Let’s put every site on one screen.

Tell us how many projects and sites you run. We will walk you through the system on a call and suggest where a pilot would pay back first.

Book a free demo on WhatsApp
Phone and WhatsApp: +91 92569 97690 Email: flip.retail1@gmail.com B-2, B203 Brij Villa, Rajendra Marg, Bapu Nagar, Jaipur 302015, India