What is committed cost on a construction project?
Committed cost is money you have already promised to spend but have not yet been billed for: purchase orders placed, work orders issued, machines on hire. Budget minus actual cost minus committed cost is the true balance left on a project.
A project can look healthy on paid bills while the orders already placed have taken it over budget. Committed cost is the figure that shows this before the bills arrive.
Balance = budget − actual cost − committed cost
Budget 8.40 million. Actual cost to date 4.91 million. Orders placed but not yet received 0.62 million. The real balance is 2.87 million, not 3.49 million.