How much cement is needed per cubic metre of concrete?

It depends on the concrete grade and mix design. Structural concrete commonly uses roughly 300 to 450 kg of cement per cubic metre, which is about 6 to 9 bags of 50 kg. Take the figure from your approved mix design, then use it as the standard to measure actual issues against.

Also called: Cement per m³, Cement consumption norm, Cement coefficient.

The mix design fixes the cement content for each grade. Multiply it by the volume poured to get the cement the work needed that day.

Compare that with what the store issued. The difference, beyond your wastage allowance, is material that cannot be accounted for.

Formula

Cement needed = volume poured (m³) × cement content of the mix (bags per m³)

Worked example

A mix with 6.5 bags per m³, 120 m³ poured: 780 bags needed. If 842 were issued, 62 bags are over.

In ERP Infra

Average consumption per unit of work is set per material and used every day as the yardstick; anything issued above it is tracked as leakage.

Material leakage: how it works

Let’s put every site on one screen.

Tell us how many projects and sites you run. We will walk you through the system on a call and suggest where a pilot would pay back first.

Book a free demo on WhatsApp
Phone and WhatsApp: +91 92569 97690 Email: flip.retail1@gmail.com B-2, B203 Brij Villa, Rajendra Marg, Bapu Nagar, Jaipur 302015, India